Lowther-Rolton undertake feasibility study to determine the craneage and transportation requirements 18 September 2015

Lowther-Rolton were appointed by our Client to undertake a feasibility study to determine the craneage and transportation requirements for the delivery and installation of process Columns, PAUs and other process equipment items, into the live plant, as part of their Project. Engaging Lowther-Rolton at an early stage of the Project enabled the Client to consider various transport and installation options and their potential effect on other work areas of the Project. The study prepared by LR independently of specific equipment operated by any Contractor allowed various options to be considered by the Project team in the early stages and maintained flexibility for the Project.