Client: PT Petrokimia Nusantara Interindo.
Independent technical check, safety audit, including site attendance, for the installation of a Reactor comprising two sections, the top weighing 190Te. The lift utilised a Manitowoc 4600 Ringer crane mounted on a piled foundation. The Technical Audit considered the Reactor, lifting equipment and geo-technical analysis of imposed ground loadings.
Client: PT Petrokimia Nusantara Interindo.
Independent technical check, safety audit, including site attendance, for the installation of a Reactor comprising two sections, the top weighing 190Te. The lift utilised a Manitowoc 4600 Ringer crane mounted on a piled foundation. The Technical Audit considered the Reactor, lifting equipment and geo-technical analysis of imposed ground loadings.